Thornton Road to Empire Substation T-Line Rebuild Construction
					Client: Western Area Power Admin.
Location: Arizona
Completion: Date: March 2012
Scope/Description:
- 15 miles of double-circuit steel – 230 kV
 
- Double circuit steel poles, 1272 wire
 
- Foundations and direct embeds with 1 OPGW & One 7/6” static