Nerc Mitigation Stage II Construction Project

Client: Western Area Power Admin

Location: Arizona

Completion Date: March 2017

Scope/Description:

  • 32 miles of 230 kV re-conductor and structures
  • Poles = existing lattice towers
  • Install four new steel pole H-frame direct embeds
  • Install 32 miles of new 636 scooter and 954 canvas-back
  • Change 91 existent tangent structures to floating dead-end type structures